

Steven F. Udvar-Hazy Center Construction
Raising the Roof
General
contractor Hensel Phelps Co., along with the subcontractor team,
is "raising the roof" of the aviation hangar at the Steven
F. Udvar-Hazy Center. The vaulted roof of the hangar is 103 feet
high in the center, the hangar is 248 feet side to side-with no
center supports!
The hangar is supported
by arches or "trusses" of steel. In engineering terms,
a "truss" is a rigid framework. With their curved shape,
the trusses actually support both walls and roof of the giant hangar.
Hensel Phelps built 42 thrust blocks
for the trusses, steel and concrete bases that support the great
weight of the trusses on either side. (They are called "thrust
blocks" because the weight on the trusses causes their ends
to push out or "thrust.")
|
The
trusses are being fabricated in three sections, using steel
from America. ADF International Inc., the structural steel
subcontractor for the project, performs the initial fabrication
in Montreal, Canada. The long tubular chords of steel and
connecting purlins are then trucked to northern Virginia.
Image courtesy of ADF International Inc.
|
 |
At the construction site, on customized jigs, iron workers finish
the assemblies: two side sections and one center section for
each truss.
Photo by Mark Avino, NASM;
©2002, Smithsonian Institution |
 |
Upon completion, the 58-foot side sections, each weighing approximately
35 tons, are taken by crane to the thrust blocks that will
support them, starting on the far north end of the hangar.
Photo by Mark Avino, NASM;
©2002, Smithsonian Institution |
 |
Very carefully, a side truss section is positioned so that the
"lower lip" rests on its thrust block. A "guide
pin" is lined up with a center hole in the base. Here
the sections will wait in a lowered position. Large bolts
will hold the parts together when raised.
Photo by Mark Avino, NASM;
©2002, Smithsonian Institution |

 |
ADF joins four side sections into a "block," one block
on the east and one on the west. Galvanized acoustical decking
is welded and screwed into place, lining the trusses with
the inner most layer of the ceiling-roofing sandwich.
Photo by Smithsonian staff;
©2002, Smithsonian Institution |
 |
A block of side sections is ready to be lifted into place.
Photo by Smithsonian staff;
©2002, Smithsonian Institution |

 | Late on the afternoon of January 28, 2002, ADF lifted the eastern
block of side sections, using two cranes. The cranes' cables
were connected to a strong-back, which distributed the significant
weight between the two cranes. At each of four thrust blocks,
curved guide pins slid into place (see photo above) as the
sides slowly rose. Large bolts were fastened in place, securing
the steel to its concrete bases. Four shoring towers added
temporary support. The crew finished work on this unusually
warm winter evening as the full moon was rising.
Drawing courtesy of Hensel Phelps Construction
Co.
Photo by Mark Avino, NASM;
©2002, Smithsonian Institution |
|
On January 29, the same crews erected the western block of side
trusses, and they did it in one hour.
Photo by Mark Avino, NASM;
©2002, Smithsonian Institution |
 |
To complete the arches, ADF is fabricating 228-foot center sections
on a larger jig just south of the hangar construction area.
As each 70-ton section is completed, it is walked by crane
to a temporary resting place.
Photo by Mark Avino, NASM;
©2002 Smithsonian Institution |
 |
On January 30, at about 1:30 p.m., a single 188-foot crane--higher
than an 18-story building--picked up the first center section
and headed for the waiting side sections. Two men on each
end of the truss walked along with the crane, grasping guide
lines as the load was maneuvered down the hangar.
Photo by Mark Avino, NASM;
©2002 Smithsonian Institution |
|
Painstakingly, the crane operator, under the direction of an ADF choreographer,
aligned the center section with the northern most pair of
side trusses. Two steel workers waited on both the east and
west sides, perched atop the raised steel, equipped with the
tools of their trade, ready to connect the giant steel members.
Drawing courtesy of Hensel Phelps Construction
Co. |
 |
Also on each side was another ADF worker in a boom lift. At 2:35
p.m., the three men on the west side grasped the center section
and began the hard job of fitting the steel into waiting slots
and connecting the bolts.
Photo by Tatiana Haagensen, HOK;
©2002 Smithsonian Institution |
 |
Just after 3:00, the east-side team began their work. The first
truss-number 68-was complete!
Photo by Tatiana
Haagensen, HOK;
©2002 Smithsonian Institution |
 |
By mid-summer, the 984-foot-long hangar will be under roof and
closed in. When the museum opens in December 2003, aircraft
will hang from the trusses, and the arched roof will shelter
this unique and historic collection. |
View the Behind the Scenes article on the raising
of the last aviation hangar truss.
Back to Udvar-Hazy Center Behind the Scenes
Page
YouCanHelpNASM@si.edu
|